Memorial Field West Stand demo going ahead?

Several years ago Dartmouth planned to demolish and replace the terraced steel-and-concrete seating structure of the main stand at Memorial Field, preserving the screening brick facade on Crosby Street.

Then, in December of 2008, Provost Scherr wrote in a letter that “[t]he full renovation of the West Stands was originally scheduled for November 2008-August 2009. The decision to defer is due to the current global economic downturn, which is impacting Dartmouth, as well as many other institutions.”

Memorial Field

View to the north under the stands.

Now a baseball recruiting presentation (pdf), undated but describing the 2012 season, provides this interesting tidbit:

Project Cost Year Completed
[…] […] […]
Memorial Field West Stand Replacement $ 16 Million Sept. 2012

Hmmm.

—–

[Update 11.17.2012: Broken link to baseball presentation fixed.]

[Update 07.16.2012: In other words, this is a strangely specific mistake for the baseball team to make. One can imagine how an old date, such as August of 2009, might have been left in the presentation over the years; but was the project ever scheduled to finish during September of 2012? Aren’t the $16 million price tag and the September date rather arbitrary to be pure oversights? Who knows where this information came from…]